  GOALS FOR 2007-08

POWER SECTOR :
 

1. Generation
•  Power Load Factor (PLF) of Gujarat State Electricity Corporation Ltd.
   (GSECL) Plants will be improved from 70% to 78%.
•  Kutch Lignite Thermal Power Station (KLTPS) Unit No.-IV (75 MW) will
   be commissioned by March-2008.
•  The combined cycle Dhuvaran-II system will be commercially commenced
    by November-2007.
•  Letter of Intent issued for Ukai, Sikka & Utaran by October-2007.

2. Transmission
•  50 new Sub-stations will be completed.
•  Transmission loss would be reduced to 4.1%.

3. Distribution
•  Total revenue will be increased up to Rs.14,400 crores for the year.
•  Distribution losses will be reduced by 4% on average of all Distribution
   Companies. (For PGVCL 6%).


OIL & GAS SECTOR :

•  Release of 50,000 new domestic PNG connections
•  Letter of Intent (LoI) will be issued for Gujarat State Energy Generation Ltd.
   (GSEG) & Gujarat Pipavav Power Company (GPPC) by October-2007.
•  Gas Grid Project : expansion in new sections like Baroda-Halol (Godhra),
   Bhavnagar, Mundra and Surendranagar


RENEWABLE SOURCES OF ENERGY:

•  Installation of 600 Nos. of Solar Photovoltaic Street Lights in various Nagar
   Palikas and 700 Nos. of Solar Photovoltaic Street Lights in the colonies of
   Salt workers (Agarias) in the State.
•  A MoU for implementation of ECO-III Project will be signed in May 2007 and
   Project will be launched by October 2007 for phase wise implementation.
•  Wind Energy capacity of state is 772 M.W. as on 30/09/07.
 